Examination of Time Management Techniques Derived From Critical Path Method (CPM) Findings to Meet the Completion Goal For the Construction Project of the Central Kalimantan Public School
DOI:
https://doi.org/10.55927/fjst.v5i7.118Keywords:
Execution Time, Site Conditions, Peat Soil, Critical Path Method (CPM), Critical Path.Abstract
The Central Kalimantan Public School Construction Project involves building activities at several sites with varying conditions, such as peat soil, difficulties in transportation, severe weather, and limitations in material supply. These factors could affect the overall expenses and timelines of the project, highlighting the need to analyze their impact on how well the project performs. This research intends to examine the timeline for the Central Kalimantan Public School Construction Project and assess how well the schedule is monitored through the Critical Path Method (CPM). A case study was conducted using both descriptive and evaluative techniques. The information gathered included the original contract, any modifications, schedules, and reports on work progress. The CPM analysis was performed to pinpoint the critical path and the key activities that could affect the project's duration. The findings suggest that the conditions of the site have an effect on the project's timeline. The CPM analysis identified vital activities that need to be managed to achieve the project's completion goals. Using the CPM approach can help in controlling the schedule and in making informed decisions during the project's implementation
References
Abrar, H. (2011). Project Management: Project Planning, Scheduling, and Control. Yogyakarta: Andi.
Aprianto, A. (2020). Development of Standard Operating Procedures for the Maintenance and Care Management Process of High-Rise Buildings. Master’s Thesis in Engineering, Universitas 17 Agustus 1945 Surabaya.
National Standardization Agency of Indonesia (BSN). (2019). SNI 1726:2019 Procedures for Earthquake-Resistant Design of Building and Non-Building Structures. Jakarta: BSN.
National Standardization Agency of Indonesia (BSN). (2019). SNI 2847:2019 Structural Concrete Requirements for Buildings. Jakarta: BSN.
National Standardization Agency of Indonesia (BSN). (2020). SNI 8460:2020 Geotechnical Design Requirements. Jakarta: BSN.
Dipohusodo, I. (1996). Project and Construction Management. Yogyakarta: Kanisius.
Ervianto, W. I. (2005). Construction Project Management. Yogyakarta: Andi.
Ervianto, W. I. (2017). Analysis of Work Changes (Change Orders) on Construction Project Performance. Journal of Civil Engineering, 24(2), 87–96.
Heizer, J., Render, B., & Munson, C. (2017). Operations Management. New Jersey: Pearson Education.
Husen, A. (2011). Project Management. Yogyakarta: Andi.
Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. New Jersey: John Wiley & Sons.
Ministry of Public Works and Public Housing of the Republic of Indonesia. (2020). Regulation of the Minister of Public Works and Public Housing Number 14 of 2020 concerning Standards and Guidelines for the Procurement of Construction Services through Providers. Jakarta. Moder, J. J., Phillips, C. R., & Davis, E. W. (1983). Project Management with CPM, PERT and Precedence Diagramming. New York: Van Nostrand Reinhold.
Nugraha, P., Natan, I., & Sutjipto, R. (1985). Construction Project Management. Surabaya: Kartika Yudha.
Government of the Republic of Indonesia. (2017). Law Number 2 of 2017 concerning Construction Services. Jakarta.
Prasetyo, A., & Nugroho, S. (2021). Analysis of the Impact of Design Changes on the Cost and Execution Time of Building Projects. Jurnal Rekayasa Sipil, 15(1), 45–53.
Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (7th Edition). Pennsylvania: PMI.
Putra, R., & Kurniawan, A. (2022). Analysis of Project Schedule Performance Using the Critical Path Method (CPM). Jurnal Teknik Sipil dan Perencanaan, 24(1), 55–63.
Render, B., Stair, R. M., & Hanna, M. E. (2012). Quantitative Analysis for Management. New Jersey: Pearson Education.
Santoso, B. (2009). Project Management: Concepts and Implementation. Yogyakarta: Graha Ilmu.
Soeharto, I. (1995). Project Management: From Conceptual to Operational. Jakarta: Erlangga.
Soeharto, I. (1999). Industrial Project Management. Jakarta: Erlangga.
Sunggono, K. (1984). Civil Engineering Book. Bandung: Nova.
Suryolelono, K. B. (2004). Foundation Engineering I. Yogyakarta: Beta Offset.
Susanti, D., & Hidayat, T. (2020). The Influence of Contract Addenda on Construction Project Performance. Jurnal Konstruksia, 11(2), 101–109.
Widiasanti, I., & Lenggogeni. (2013). Construction Management. Bandung: Remaja Rosdakarya.
Widhiarto, H. (2014). Evaluation of Construction Project Time and Cost Management Using the Critical Path Method (CPM). Jurnal Teknik Sipil Universitas 17 Agustus 1945 Surabaya.
Witjaksana, B., & Reresi, S. P. (2012). Project Cost Analysis Using the Earned Value Method in the Performance Process. Journal of Civil Engineering, Universitas 17 Agustus 1945 Surabaya, 5(2), 45–56.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Vendy Eka Saputra, Budi Witjaksana, Andi Patriadi

This work is licensed under a Creative Commons Attribution 4.0 International License.