Analysis of Project Time Implementation on Dominant Variables Influencing DED Development Performance Using the CPM (Critical Path Method) Method in the Design and Build Contract in the Ministry of Health's Batch 3 PHTC Program (Case Study: Construction of the West Muna District Hospital)
DOI:
https://doi.org/10.55927/fjst.v5i7.102Keywords:
Design and Build, Detailed Engineering Design, Site Condition Compatibility, DED Development Performance, Critical Path Method.Abstract
This study aims to analyze the factors influencing the Detailed Engineering Design (DED) Development Performance for the West Muna Regency Regional General Hospital (RSUD) construction project using the Design and Build method, as well as the implications of these dominant factors on project implementation time. The research variables consist of Basic Design Quality (X1), Compliance Level with the DKPPK (X2), and Conformity to Field Conditions (X3) on DED Development Performance (Y). Data were obtained from 31 respondents consisting of the PPK (Commissioner of Works), the Ministry of Health Technical Team, Construction Management Consultants, Design Consultants, and Design and Build Service Providers. The CPM analysis results indicate a project completion duration of 343 days, a 48-day deviation from the remaining contract duration of 295 days. The project's critical path consists of planning and permitting, foundations, earthworks, floor structures 1–3, floor architecture 3, attached interiors 3, loose furniture 3, testing and commissioning, and handover. This study concludes that suitability of field conditions is the most dominant factor influencing the performance of DED development and has direct implications for achieving project implementation timelines
References
Abdullah, A. (2022). Preparation of Detailed Engineering Design (DED) for the Environmental Laboratory Building in North Kalimantan Province. 1(1), 29–37.
Almeida, F., & Introduction. (2026). Editorial: Performing a structural equation modeling (SEM) in innovation science studies. 16(6), 1005–1011. https://doi.org/10.1108/IJIS-12-2024-289
Ardhiansyah, W., Tjendani, H. T., & Witjaksana, B. (2023). Analysis of Contractor Performance on Stakeholder Satisfaction in Construction Expenditure Projects Rehabilitation of Malang. 4(1).
Construction Project Management. (n.d.).
Desain, P., & Kemenkes, T. I. M. T. (n.d.). SITE PLAN COMPARISON MATRIX.
Eka, I., Lestari, W., Sumajouw, M. D. J., & Rondonuwu, S. G. (2021). STUDY OF INTEGRATED DESIGN AND BUILD CONTRACTS. CASE STUDY: CONSTRUCTION OF NEW YOGYAKARTA INTERNATIONAL AIRPORT (NYIA) UNDERPASS. 11(1).
Hair, J., & Alamer, A. (2022). Research Methods in Applied Linguistics: Partial Least Squares Structural Equation Modeling (PLS-SEM) in second language and education research: Guidelines using an applied example. Research Methods in Applied Linguistics, 1(3), 100027. https://doi.org/10.1016/j.rmal.2022.100027
Hasyim, F. A., Supardi, S., Studi, P., Sipil, T., Teknik, F., Muslim, U., & Makassar, K. (2024). Evaluation of Construction Project Implementation Based on LKPP Regulation No. 12 of 2019 Using the Structural Equivalence Modeling (SEM) Method. 9(3), 255–264.
Health, K., & Ministry of Health, H. (2026). Quick Wins /.
Hera, S. H., Purwanggono, B., & Ulkhaq, M. M. (n.d.). INTEGRATED LABORATORY, FACULTY OF ENGINEERING, UNDIP.
Hyun, H., Kim, H., Lee, H., Park, M., & Lee, J. (2020). Integrated Design Process for Modular Construction Projects to Reduce Rework. 1–19.
Icuk, B., Sakir, M., & Si, M. (n.d.). Qualitative, Mixed Method.
Ismail, N. B., & Teknikal, U. (2019). CLAIM MANAGEMENT FRAMEWORK UNDER FIDIC 2017: 7(1), 385–394.
Jariski, M., Indonesia, U., Communication, B., & Management, P. (2025). EVALUATION OF RISK-BASED COMMUNICATION MANAGEMENT IN PT XYZ DESIGN BUILDING PROJECT TO IMPROVE TIME. 4(5), 186–194.
Kartiwan, T. (2025). Building auditability in design-build construction contract control.
Manurung, E., Dalam, E., & Konstruksi, P. (2025). Scientific Research Journal. 2(7), 3181–3187.
Ministry of Public Works and Public Housing, M., Dan, U., Rakyat, P., & Indonesia, R. (2020). Minister of Public Works and Public Housing of the Republic of Indonesia.
No Title. (2017).
Nurcholis, M., Witjaksana, B., & Tjendani, H. T. (2023). CONTRACTOR SELECTION Criteria: FACTORS OF PT. THE INFLUENCE OF WASIS NUGRAHA’S WORKS PERFORMANCE OF THE TLOGOMAS FAMILY BRIDGE. 4(1), 15–28.
Nurdianti, W., Studi, P., Teknik, M., Teknik, F., Islam, U., & Agung, S. (2025). EVALUATION OF THE APPLICATION OF THE DESIGN AND BUILD METHOD IN THE STADIUM CONSTRUCTION PROJECT.
Permadi, S. C., & Wiguna, I. P. A. (2025). Analysis of Factors Affecting Delays in Construction Projects in the Upstream Oil and Gas Industry of South Sumatra. 5(12), 14647–14664.
Prasetiya, P., Count, W., Count, C., Count, P., Size, F., Date, S., & Date, R. (2024). 3394 Words Al-Huda Mosque, Merdeka University, Malang: Design and Build Project.
Project Management, P. M., & 2021. (n.d.). 804007527-PMP-7th-Edition.pdf.
Puryanto, M., Research, U., & Pls, S. (n.d.). No Title.
Qordhowi, A. F. Y. Al. (2024). No Title. 09.
Ramadhan, J. S. (2025). Impact of Change Orders on Cost Overruns and Delays in Large-Scale Construction Projects. 15(1), 20291–20299.
Safitri, A. S., Study, Development, P., Apslc, G., Gadjah, U., Study, C., & Project, A. B. (2021). ANALYSIS OF BUILDING PROJECT SCHEDULING USING THE CPM-PERT METHOD (CRITICAL PATH METHOD-PROGRAM EVALUATION AND REVIEW TECHNIQUE) (ANALYSIS OF BUILDING PROJECT SCHEDULING USING THE CPM-PERT METHOD) Syfa Safitri Aulia FACULTY OF CIVIL ENGINEERING AND PLANNING.
Sagaf, D. A. N., & Praktik, T. D. A. N. (n.d.). QUANTITATIVE RESEARCH METHODOLOGY, (2025th ed.).
Salsabila, G., Priana, S. E., & Hafnil, J. (2025). Analysis of Factors Causing Construction Project Delays (Case Study: RSI Ibnu Sina Padang Panjang). 1(1), 50–58.
Sari, E. M., Irawan, A. P., Wibowo, M. A., Purwanto, S. K., Sutawidjaya, A. H., Dewi, M. P., & Santoso, J. T. (2024). Design bid build to integrated project delivery: Strategic formulation to increase partnering. 8(1).
Sari, M., & Jin, O. F. (2026). CONTRACTORS AND DESIGNERS IN DESIGN AND BUILD PROJECTS Achmad Sutowo 1 Agustinus Purna Irawan 2 Endah. 7(1), 1–14. https://doi.org/10.51988/jtsc.v7i1.413
Sobirin, R., & Regency, M. R. (2025). Analysis of Time Control for Construction Work for the Construction of Dr. Sobirin Regional General Hospital, Musi Rawas Regency. 2(1), 154–168.
Surahman, A. (2020). THEORETICAL STUDY IN RESEARCH. 3(1), 49–58.
Suraji, E. B. (n.d.). Working Towards an Advanced Indonesia.
Teknologi, J., Prasetya, H. B., & Purba, H. H. (2021). Review and Analysis of Risks in Building Construction Projects: A Literature Review. 2, 95–106. https://doi.org/10.52330/jtm.v19i2.29
Wibowo, W. P., & Witjaksana, B. (2023). ANALYSIS OF CONTRACT CHANGE ORDER (CCO) COSTS IN BUILDING. 2(12).
Zhang, G., Liu, Y., Liu, J., Lan, S., & Yang, J. (2022). ScienceDirect: Causes and Statistical Characteristics of Bridge Failures: A Review. Journal of Traffic and Transportation Engineering (English Edition), 9(3), 388–406. https://doi.org/10.1016/j.jtte.2021.12.003
Zhang, W., Xu, M., Feng, Y., Mao, Z., & Yan, Z. (2024). The Effect of Procrastination on Physical Exercise among College Students—The Chain Effect of Exercise Commitment and Action Control. International Journal of Mental Health Promotion, 26(8), 611–622. https://doi.org/10.32604/ijmhp.2024.052730
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Abdul Khohar, Budi Witjaksana, Andi Patriadi

This work is licensed under a Creative Commons Attribution 4.0 International License.